S.No Client Name Description of Work
1 SJVN Post Award Review Engineering covering Inspection & Project Supervision 2X660MW Buxar TPS
2 JPDCL Project Implement Agency (PIA) for execution of loss reduction works under Sector Scheme (RDSS)
3 MPPGCL Owner's Engineering Services to MPPGCL for the installation of 1x660 MW
4 KPDCL Project Implement Agency (PIA) for execution of loss reduction works under Sector Scheme (RDSS)
5 MPPGCL Owner's Engineering Services to MPPGCL for the installation of 1x660MW ATPS
6 CSPGCL Pre and post award services for installation of 2x660 MW super critical to HTPS Korba West
7 THDCIL Complete Engineering Services for implementation of 2X660MW Khurja STPP from commissioning
8 DVC Preparation of DPR & Pre award activities for installation of 2x800MW thermal units at Koderma TPS (KTPS)
9 NCL PMC services to NCL for setting up 50MW Solar power project
10 SKS-POWER O&M Services for 2x300 MW, Phase-I, TPP of SKS Power Generation Ltd
11 DVC Revision of DPR and pre-award services for Raghunathpur II 2X660 MW
12 OPGC Detailed Project Report (DPR) and Pre award services for OPGC Stage III (2x660 MW)
13 MUNPL Pre-Award/Post Award for Installation of FGD at Meja
14 UPRVUNL Review Engg, QP approval, VA Obra -C TPS
15 UPRVUNL Review Engg, QP approval, Jawaharpur TPS
16 UPRVUNL Third party inspection services of Obra C-TPS
17 UPRVUNL Third party inspection services of Jawaharpur TPS
18 DVC Performance Evaluation of DVC Mejia 3X210 MW units for R&M works
19 MAHAGENCO Assessment study for feedwater system at 3x660 MW KTPS, Koradi
20 UPRVUNL NTPC consultancy services to UPRVUNL for O&M support of 1x660 MW Harduaganj TPS
21 UPRVUNL Commissioning support and PG test reports of Harduaganj TPS, Aligarh
22 TNPGCL Technical Consultation to improve the heat rate and reduce boiler tube failures
23 GSECL Technical audit of Wanakbori TPS (7X210 MW & 1X800 MW)
24 Reliance Industries Limited Audit of Coal and Biomass Handling Units at HMD and DMD - RIL
25 CSPGCL PG test for R&M of ESP of 4X210MW HTPS Korba-West
26 HPGCL Pre and Post Overhaul Boiler, Turbine and Cooling Tower at Panipat, Hisar
27 RRVUNL Technical Audit of 6x250 MW, Suratgarh TPS, Rajasthan
28 JITPL Technical Audit of 2x600 MW, Jindal India Thermal Power Limited, Angul